15+HIGH PROJECT UPDATES

WORK ON HIGH STREET BEGINS MONDAY, MARCH 27. WORK WILL START AT 13TH AVE CREATING LANE RESTRICTIONS MOVING NORTH IN 250FT INCREMENTS AS WORK PROGRESSES. 

 

March 2017: Phase I Infrastructure Work to Begin

**Work on High Street is scheduled to be completed by August 2017**

mARCH 2017 - jULY 2018  

            fenced construction area east of high                                   

**Construction fencing will remain in place until July 2018**
Impacts.jpg

what improvements are coming in this phase?

  • New storm sewer on High Street
  • New water line at 16th-17th Avenue
  • Rehabilitated sanitary sewer on Pearl Street
  • Burial of existing overhead utilities on Pearl Street
  • Street reconstruction and opening of 16th Avenue to High Street
 

construction timeline/next steps

 

  • March 2017 - July 2018 -  Infrastructure Phase I

  • March 2017

    • Lane restrictions begin on High Street starting at 13th Ave to prepare for upcoming work

    • Fencing off area east of High for construction site

  • April 2017
    • Work on High Street begins
    • Fencing and maintenance of traffic signage installed
  • Future 

    • Rehabilitation of existing sanitary sewer on Pearl Alley begins

    • Timeline of development not yet determined 

    • Phase II Infrastructure TBD

    • Street reconstruction and opening 16th Avenue at High Street 

    • Burial of utility lines on Pearl Street