Pedestrian Access Updates

- Beginning Thursday, June 29th, construction work on the west side of High Street between 16th-17th Ave will be wrapping up and flipping over to the east side. Pedestrian access on the west side will return to normal conditions.

- Pedestrian access will remain closed between 16th-17th Ave on the east side of High Street through early-mid August.  

Project Updates

 

MARCH 2017 - AUGUST 2017

PHASE I INFRASTRUCTURE WORK ON HIGH STREET

**Work on High Street is scheduled to be completed by August 2017**

MARCH 2017 - JULY 2018  

                              FENCED CONSTRUCTION AREA EAST OF HIGH                                   

**Construction fencing will remain in place until July 2018**

Impacts.jpg

Improvements Coming in this Phase:

New storm sewer on High Street

New water line at 16th-17th Avenue

Rehabilitated sanitary sewer on Pearl Street

Burial of existing overhead utilities on Pearl Street

Street reconstruction and opening of 16th Avenue to High Street

 

Construction Timeline

 

  • March 2017 - July 2018 -  Infrastructure Phase I

  • March 2017

    • Lane restrictions begin on High Street starting at 13th Ave to prepare for upcoming work

    • Fencing off area east of High for construction site

  • April 2017

    • Work on High Street begins
    • Fencing and maintenance of traffic signage installed
  • Future 

    • Rehabilitation of existing sanitary sewer on Pearl Alley begins

    • Timeline of development not yet determined 

    • Phase II Infrastructure TBD

    • Street reconstruction and opening 16th Avenue at High Street 

    • Burial of utility lines on Pearl Street